IS 1200 Part 13 Painting & Colour Measurement Rules

How civil engineers, quantity surveyors, and colour bill auditors calculate net paintable area, apply door/window deductions, and catch overbilling.

1. Standard Door, Window & Opening Deduction Rules

The single biggest source of overbilling in contractor colour bills is skipping opening deductions. Under IS 1200 Part 13 (Whitewashing, Colour Washing, Distempering & Painting), deductions depend on the opening size:

Opening Area (Sq.m / Sq.ft) Deduction Rule Jambs, Soffits & Sills
≤ 0.5 sq.m (≤ 5.38 sq.ft) No deduction Not measured separately
0.5 to 3.0 sq.m (5.38–32.29 sq.ft) Deduct 1 face only (50% of two faces) Included (not added separately)
> 3.0 sq.m (> 32.29 sq.ft) 100% full deduction on both faces Measured & added separately

2. Surface Multiplication Coefficients (Non-Flat Surfaces)

For shutters, grills, and corrugated sheets, flat projected area is multiplied by standard factors to reflect actual painted surface area:

Surface Type Factor (Each Side) Notes
Flush / Plain Wood Door Shutter 1.00 × (2.0 both sides) Frames measured separately if required
Panelled / Ledged & Braced Door 1.30 × per side Covers moulding & panel recesses
Corrugated GI / Asbestos Sheet 1.14 × per side Accounts for wave profile
MS Grill / Collapsible Gate 1.00 × to 1.50 × flat Depending on bar density & BOQ

3. Worked Example: Room Colour Measurement

Consider a bedroom of 12 ft × 10 ft with 10 ft clear ceiling height, containing 1 door (3 ft × 7 ft = 21 sq.ft) and 1 large window (6 ft × 6 ft = 36 sq.ft):

  • Gross Wall Area = 2 × (12 + 10) × 10 = 440 sq.ft
  • Ceiling Area = 12 × 10 = 120 sq.ft
  • Door Deduction = 21 sq.ft (0.5–3 sq.m band: deduct 1 face on room side = -10.5 sq.ft if painted both sides, or -21 sq.ft if only 1 wall face)
  • Window Deduction = 36 sq.ft (> 3 sq.m: 100% deducted = -36 sq.ft; jambs measured separately)

Want our engineers to verify your entire building's Measurement Book? Submit your bill details below to book an audit or request our fee quote.

Get Your Colour Bill Audited Per IS 1200

Share your project details below. Our measurement specialist will respond within 2 business hours.

100% confidential. Your BOQ, drawings, and contractor bills are never shared with third parties.

Call Now WhatsApp Audit